ANEEL fine the CHESF for delay in transmission

29/10/2012

This article was translated by an automatic translation system, and was therefore not reviewed by people.




The National Agency of Electric Energy (ANEEL) dismissed the appeal brought by the Hydroelectric Company of São Francisco (CHESF) and kept fine in the amount of R$ 2.2 million for breach of the implementation schedule of works for the auction lot B No. 06/2010. The measure was taken during the Board of Public Meeting last Tuesday. The decision ends the possibility of enterprise resource administratively.

CHESF claimed that the delay in completion of the projects was due to the shallowness of information available for the auction and the delay of the organs in the analysis of environmental claims. The supervision of the Agency found that the company had the opportunity to review the information before the auction to assess the risk of any existing faults and not even having participated in the event. Regarding the process of licensing, inspection reported that portion of the delay was due to the company's delay in submitting documents.

According to the Agency, the delay in the completion of these works will be at least 17 months and will impact directly the entry of 14 wind farms that participated in the auction 03/2009. Lot B Auction No. 06/2010 consists of the transmission line Igaporã - Bom Jesus da Lapa II and Igaporã substation, located in Bahia.


Source: ANEEL

Our news are removed entirely from the sites of our partners. For this reason, we can not change their content even in cases of typos.

This article was translated by an automatic translation system, and was therefore not reviewed by people.

Important:
The JurisWay site does not interfere in the work provided by doctrine, why only reflect the opinions, ideas and concepts of their authors.


  Subjects list
 
  Copyright (c) 2006-2009. JurisWay - All rights reserved.